Finished framing and building paper cladding

Putting up the purlins with dad
The tarpaulin roof survived the past week of crap weather, but only due to the fact I had to poke the water pockets with a stick. The tiny amount of moisture that got in was dry the same day so no worries there. The forecast was for worse though so I made it a mission to get the roof ready for cladding. It rained very very hard the whole weekend, but thankfully I had it parked in the factory - for the last time, now the roof is watertight!!

fence pails and random purlins

The roof has 2x2, 3x2, and mainly 4x2 purlins. Half is exterior grade but hey wood is wood to me, as long as I’m recycling as much as possible. I strengthened with strap bracing, not very strongly, but it’s mainly for the paper anyway. I used fence pails for screw points for 3mm MDF - the kitchen place next door gets a couple of sheets per delivery so dad and I worked out a cheap and lightweight way to get lots of nogging for it - otherwise it warps like a piece of cardboard. So the $10 spent on fencing materials saves me $50 worth of ply done.


The loft bed was pretty easy to install since it was resting on top of the back plate, with 790mm on each side. It also meant we had a platform to use when installing the purlins.

It has 6mm ply as a temp flooring, free from the side of the road.

the loft bed platform - the square is a fixing for an opening window

I also nailed off a whole heap of boxes - 23 so far and probably another for good luck - which will become the stairs to the loft. I got these all free, as industrial waste. Pretty awesome storage, and the area directly underneath the loft bed will become a bookshelf. I bought some little woven baskets to put my clothes in, and whatever else I use them for, as all my clothes take up a whopping five boxes. At least everything will have a place!

I just have to pick up some ply for the stairs and something to use for the bookshelf, which my dad probably has hoarded somewhere.  So now I'm just waiting to have all the ply in one place (eg inside the tiny home) and then I can get cracking with my pink batts. I got all the batts for free, minus $5 worth of offcuts (which ultimately I didn't need) and half a bag of pink batts squares which came with my long run roofing with the building paper. I had JUST enough building paper.. if it were anyone else they probably would have bought more, but I managed to scrounge enough to fix it up - hopefully. It isn't very professional looking!! But so long as it keeps the water out it's doing its job. Better get some rest now, it's been a very long weekend.


Sunday, 7 December 2014

Almost finished building!

Trying to get the pup to pose

The loft framework and windows all packed up, as well as the skeletal structural view of inside

All papered up and ready to tarp

Tarp finally up - used nails on sticks to get the height, sounded more fun than it was..

Friday, 5 December 2014

Latest progress report

(Onsite at the build, everyone was in the parking lot when I finally had enough manpower to lift the walls. That just meant we had to carry them an extra 10 or so metres, which is okay with four people per wall - two people is a shuffle dance at a distance of 1-2m only.

So the walls went up, the 150mm galv coach screws went into the sills to the subfloor, and a few nails gunned into the sides of the walls for good luck.
I still have the make the cantilevered 2nd floor but that's another mission for another day.

Here you can see the strap bracing in most of it's glory (forgot a progress report pic as I was too busy entertaining friends (read: talking too much) and getting them to help move the 6m lengths of 2x4s I had "resting" on my stairs. Unfortunately this was the only place I could 'hide' them and they got a bit warped over the two weeks they sat there. Really annoying but hey it's my fault, and I hope I learn from my mistakes! The 2x4s that are visible in the doorway are half my roof purlins - leftovers put to good use - and I'm sourcing 2x2s for the rest of them.

I also got the loft bed subfloor cut and my friend came over to help me try and put it together. Well, we did put it together. But it is seriously warped. So to fix it I'm borrowing two of my flatmate's 5kg dumbbells and weighing down the high ends.. Hopefully it rains overnight and it will start looking to be a better shape, but I can put it in the trailer like that tomorrow to flatten it further. I also spent $30 buying more galv brackets and screws so the bed is fully supported both sides.


I'm a bit interested to see how much extra work the loft area will be.. I have a strange angled window I can put near my head - I did get the angle close enough to fit it accurately without it looking odd, but the amount of extra work might make it not worth it. Especially since there is a 600mm square opening window on the loft bit above the massive window pictured. Once the loft floor is installed it will probably be easier to tell. But my biggest concern is that as the back plate is made, the floor may need to be notched. Mildly disturbing but I don't have the manpower to find out just yet.

My next main mission is to start cutting the plasterboard for the stairs - which are to be made out of those boxes on the bottom left of the picture just above. Got them free from the neighbours' wood pile, enough to make all my stairs and then a couple of 6x9 holders to boot.

All my window flashing arrived this week too. Turns out the roofing place are worse with a tape measure than me, and NONE of their measurements are correct. Thankfully there is more than I need, not less, so just another annoying tin snip and angle grinder with cut off blade exercise. Took it in to get them to fix one (it was 1220mm, meant to be 605mm..!) and it took them forever and they were cutting by hand so I gave up before they could cut the rest.

Better go finish putting up this building paper so I can put the tarp on the roof. My flatmate's dad is coming over in a few weeks and has offered to install my roof - yay! Already at 4.2m, the walls are too high for me to work on easily so I'm glad to have some professional help from someone who knows what they are doing!! Okay better get back to work. JAYA JAGANNATHA!